
The bridge remains part of an active construction site and is not yet open to the public. While many structural components, including the Hot-Mix Asphalt roadway surface, are substantially complete, several critical items must be finalized prior to the safe opening of the roadway and pedestrian facilities.
Remaining Work Includes:
- Landscape restoration
- Installation of permanent pavement markings
- Guardrail installation
- Installation of safety-related pedestrian handrails
- Completion of final punch list items
Safety Notice:
Although the concrete parapet walls have been installed, they are only 28 inches in height and do not meet minimum safety standards. Until the permanent handrails are installed and all safety measures are in place, both vehicular and pedestrian access to the bridge will remain restricted.
Project Progress:
The contractor has remained active throughout the winter months and, as a result, is ahead of the original September 2025 completion schedule. The project team continues working diligently to complete all remaining work and open the bridge to the public as soon as it is safe to do so.
We appreciate the public’s patience and understanding as we work to complete this important infrastructure project safely and efficiently.