Pier Construction and Cofferdam Removal Progress

Week in Review: Accomplishments and Progress

This past week the contractor successfully poured the concrete stem wall for the west pier, followed by framing, placing rebar, and pouring the cap. On the east side, the contractor completed backfilling the east pier and began removing the cofferdam. Additionally, temporary fencing was installed on the south side of Oak Spring Road, east of the river, ensuring the safety of the area during ongoing construction.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to backfill the west pier and remove the causeway to prepare for excavation of the east abutment. Rip rap installation at the east abutment will also commence to enhance erosion control. The removal of the remaining cofferdams is expected to be completed as part of the next phase of work.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading