Causeway Removal and Abutment Construction Progress

Week in Review: Accomplishments and Progress

This past week, the contractor successfully completed the removal of the west causeway and the existing abutments. Excavation began for the proposed west abutment, along with the installation of rip rap to stabilize the site. The contractor also finished driving the shell piles for the east abutment, and following that, tied rebar, framed, and poured the concrete for the east abutment.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to continue excavating for the proposed west abutment and proceed with the installation of rip rap for stabilization. Rip rap installation for the east abutment is expected to be completed. Additionally, the contractor will focus on driving the shell piles for the west abutment, followed by setting rebar, framing, and pouring the concrete for the west abutment.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading