Week in Review: Accomplishments and Progress
Last week, the contractor continued framing and pouring the concrete retaining walls and progressed on framing the bridge deck. A milestone was reached with the completion of the storm sewer removal and replacement.
Looking Ahead: Planned Activities
This week, the contractor plans to complete the framing, setting of rebar, and pouring of the concrete retaining walls. Work on the bridge deck will also advance, with the contractor anticipating setting the rebar to prepare for the next stages of construction.
Community Impact: What to Expect
With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.