Bridge Deck Pour and Approach Preparation

Week in Review: Accomplishments and Progress

This week, the contractor completed adjustments to the reinforcement bar for the bridge deck and successfully poured the bridge deck. Note: the bridge is not anticipated to be available for use until summer 2025. Additionally, the contractor graded and framed the approach footings, preparing for further work on the bridge approaches.

Looking Ahead: Planned Activities

Next week, the contractor plans to pour the approach footings and proceed with grading and pouring the approach slabs. Planned work will also include patching the retaining walls and placing temporary seed and blanket beyond the retaining walls for erosion control. Coordination with MCI will continue for the replacement of their underground conduit and fiber optic cable along the south side of the bridge.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading