Week in Review: Accomplishments and Progress
Last week, the contractor successfully poured the concrete for the approach slabs. The contractor also continued removing the concrete forms from the bridge deck, preparing for subsequent work.
Looking Ahead: Planned Activities
This week, the contractor plans to continue removing the concrete forms from the bridge deck. Additionally, framing for the sidewalk on the approach slabs is anticipated to begin.
Community Impact: What to Expect
With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.