Curb, Sidewalk, and Subgrade Work

Week in Review: Accomplishments and Progress

This week, the contractor completed fine grading of the aggregate subgrade for the roadway. Aggregate subgrade was also placed for the proposed sidewalk, and the aggregate base course for the barrier curb was installed. Framing and pouring of both the concrete curb and concrete sidewalk were completed.

Looking Ahead: Planned Work

Next week, the utility company subcontractor for MCI is scheduled to complete the installation of underground conduit and fiber optic cable along the south side of the project.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading