Week in Review: Accomplishments and Progress
This past week, the contractor continued work on framing and pouring the concrete retaining walls and continued work on the framing of the bridge deck.
Looking Ahead: Planned Activities
In the upcoming week, the contractor plans to complete the framing and pouring of the retaining walls and finalize the framing of the bridge deck. Following this, work will begin on setting rebar for the bridge deck. Additionally, the contractor anticipates completing the storm sewer removal and replacement.
Community Impact: What to Expect
With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.