Abutment and Retaining Wall Construction Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued with the excavation for the proposed west abutment and progressed on the installation of rip rap to stabilize the area. Rip rap placement for the east abutment was completed, providing added erosion control. On the west side, the contractor drove the shell piles for the west abutment and began driving the H-piles for the retaining wall east of the river.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to complete driving the shell piles for the west abutment. Following this, work will proceed with setting the rebar, framing, and pouring the concrete for the west abutment. Additionally, the contractor will continue driving the H-piles for the retaining wall east of the river, further supporting the project’s stability and safety.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading