Causeway Removal and Abutment Excavation Progress

Week in Review: Accomplishments and Progress

This past week, the contractor completed the removal of the east causeway. Excavation began for the proposed east abutment, with the initial installation of rip rap underway to help control erosion. Additionally, the contractor successfully completed the removal of the west cofferdam and commenced the removal of the west causeway.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to complete the removal of the west causeway and continue with the removal of the existing abutments. Excavation for the proposed west abutment will begin, accompanied by the installation of rip rap to stabilize the site. The contractor also anticipates driving the shell piles for the east abutment.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading