Pier and Cofferdam Construction Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued work on the Oak Spring Road Bridge Replacement project. Earth excavation in the west cofferdam for the west pier was completed, and all shell piles for the east pier were successfully driven. In addition, the contractor completed driving the test piles for both the west pier and the west abutment. Concrete forms and rebar were installed for the east pier, preparing the site for the next phase of construction.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to pour the concrete stem for the east pier. Work will continue on the west pier with the completion of driving shell piles. The contractor also anticipates framing and pouring the concrete cap for the east pier.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading