Bridge Demolition and Causeway Construction Progress

Week in Review: Accomplishments and Progress

This past week, the contractor successfully completed the demolition of the existing bridge deck, beams, and piers for all four bridge spans. Additionally, the tops of both existing bridge abutments were removed. The contractor constructed the causeway on the west side of the river and adjusted the turbidity curtain around the causeways on both sides of the river to maintain environmental protections. Installation of the east cofferdam for the proposed east pier began. During this process, a conflict was encountered with an MCI cable. MCI is expected to install a temporary aerial fiber optic line over the weekend to allow the contractor to proceed with the east cofferdam installation.

Looking Ahead: Planned Activities

In the upcoming week, the contractor anticipates completing the installation of the east cofferdam for the proposed east pier. Once this is achieved, dewatering, excavation, and the placement of stone within the cofferdam are expected to follow. The contractor also plans to drive test piles for the proposed east pier and east abutment. Additionally, work will begin on the installation of the west cofferdam for the proposed west pier, setting the stage for the next phase of the project.

Community Impact: What to Expect

With the road closure now in effect, residents should be aware that Oak Spring Road from east of the Des Plaines River Trail to west of Hawthorn Lane is closed to traffic for the duration of the project. This closure is necessary to ensure the safety of both the workers and the public. Your patience and understanding are greatly appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Oak Spring Road Bridge

Subscribe now to keep reading and get access to the full archive.

Continue reading